Bullers Wood Progress

Please see below an update on how the Bullers Wood School for Boys in Bromley Construction work is progressing :

If you have any further questions regarding the works currently going on please contact :

Matthew Gooderham – 07568 136453 – matthew.gooderham@kier.co.uk

Week Commencing 3rd June 2019

Temporary School Foundations are all in place ready for delivery of the units 11.06.19.

Pedestrian footpaths have been segregated, gravelled and levelled to enable safe access on site for construction staff.

Segregated Pedestrian Entrance formed and is now in use for the current school and public.

Temporary matting for the crane position has been placed on site ahead of the modular units being lifted in.